Announcement

Supervision of construction works at Corum, Turkey
25Jul2016

On 05.02.16, the commencement order for the construction works of the project “Construction of Çorum Solid Waste Management Project” was given to the Contractor İSTAÇ.

The construction works are supervised by the international consortium ENVIROPLAN (leader) – CDM SMITH – AHT Consortium and consist of the following elements:

· Çorum Solid Waste Management Facility inclusive of Sanitary landfill (phase 1 only), leachate collection system and leachate treatment plant (WWTP), Gas collection system and flaring system and auxiliary infrastructure works

· Material Recovery Facility

· Composting Plant

· Four Transfer Stations

· Civic Amenity Centre

· Non – Compliant landfill closure and rehabilitation works

The time for completion of construction works is 19 months.

The project is financed by the IPA Budget Item 13.05.02 of the General Budget of the EU and National Contribution.

The Contracting Authority is Ministry of Environment and Urbanisation, Department of EU Investments.

The End-Beneficiary is Environmental Union of Çorum Municipalities.

Photographs

Annaouncement Photo



« Back